Friday, July 22, 2011

corrections


Two things to get straight--first, the primary voltage here 11kv.  Second, the tree crew foreman's name John Owiti not Owati. There has been some problem with substandard breakers and breaker panels showing up around town, so Francis had an engineering and operations meeting this morning to show the guys the difference between the fake and the standard stuff.  By then it had started to rain, so we did some schooling on how to read work orders. The rain let up and we went to work. I was going to take the tree crew across the river to finish up the right of way they were trimming, but too much water in the river, so that didn't work. The crew found work in the compound and I helped Framcis do some wiring on the compound.  The first picture is of John Kennedy on my right and Phillip on my left. The next is of some people crossing the rive-- the same one that was a dry riverbed last week. The last is of the E & O meeting this morning.